SV-240936r879586_rule
Version
V1R2
CCIs
Any changes to the components of the application server can have significant effects on the overall security of the system. In order to ensure a prompt response to failed application installations and application server upgrades, the application server must provide an automated rollback capability that allows the system to be restored to a previous known good configuration state prior to the application installation or application server upgrade.
Interview the ISSO and/or the SA. Determine if there is a local procedure to revert to the last known good configuration in the event of failed installations and upgrades. If a procedure does not exist or is not being followed, this is a finding.
Develop and implement a site procedure to revert to the last known good configuration in the event of failed installations and upgrades.